123 Vampire Street

Build Progress Update

Scan Date

March 22, 2024

Construction Phase

Frame Installation

Next Milestone

Roof Installation - Expected April 5

Weather Conditions

Partly Cloudy, 20°C

Progress Notes

Frame installation completed ahead of schedule. Electrical and plumbing rough-in to begin next week. All materials for upcoming work have been delivered to site.